Should a contractor be liable to pay delay damages when the employer has delayed the project by a breach of contract/act of prevention and the contractor has failed to comply with the time-bar clause?
This is a common question across the GCC countries. First of
all, we need to differentiate between the legal limitation periods and the
time-bar clauses. the former are related to periods provided by express legal
provisions for rights to claimed in courts. The right holder must claim the
right within this period. the period starts to run when the right becomes due. These
periods are a matter of public policy that cannot be agreed against. People may
not change such periods by agreements. However, a contractual time-bar is
totally different. The time-bar clause is classified as condition precedent. That
is to say, the contractual right may not become in existence till such a
condition is fulfilled. In FIDIC books, time-bar clauses are condition precedents.
Back to the question, the employer may allege that the
contractor’s right has not come into existence due to non-compliance with time-bar
clauses. This applies to extension of time requests. However, if the delay was
caused by the employer’s breach of contract, several issues may also need to be
considered. The first issue is related to the causation principle. The judge /
arbitrator will need to know the main cause of the delay by using the phrase ‘but
for’. The project was supposed to be completed on time but for X. If X
is the employer’s fault, he should not be allowed damages for such a delay. The
second issue is related to the good faith principle, which can be found in
civil codes across the region. Article 246/1 of the UAE Civil Transactions Code
states that “the contract must be performed in accordance with its contents,
and in a manner consistent with the requirements of good faith”. By claiming
damages for late completion due to his own fault, the employer cannot be
performing the contract in good faith.
Comments
Post a Comment
You may comment here